How to sell to Oklahoma counties

Oklahoma counties must bid purchases over $25,000, with notice at least 10 days before the board of county commissioners opens bids, and award to the lowest and best bid. Public construction over $100,000 is advertised 21 days ahead and needs a 5% bid guarantee and 100% bonds. Retainage is up to 5% of each payment.

Oklahoma has 77 counties. County purchases of supplies, materials, equipment, road and bridge construction services and IT follow the County Purchasing Act (Title 19), and public construction follows the Public Competitive Bidding Act (Title 61). Oklahoma State University Extension's Purchasing Handbook for Oklahoma Counties explains both and is the main source here, because the official statute site could not be read.

At a glance

Topic Rule Source
Who buys Board of county commissioners awards; county purchasing agent sends notices 19 O.S. 1505
Goods and services Bids required over $25,000 19 O.S. 1505
Construction Sealed bids over $100,000; construction management trade contracts over $50,000 61 O.S. 103(A)
Notice Purchases: 10 days; construction: two weekly issues, first 21+ days ahead 19 O.S. 1505; 61 O.S. 104
Award Purchases: lowest and best; construction: lowest responsible bidder 19 O.S. 1505; 61 O.S. 103
Bid security 5% of bid on construction 61 O.S. 107
Bonds 100% performance and payment; 100% one-year maintenance 61 O.S. 113
Prevailing wage No state law (invalidated 1995) U.S. DOL
Retainage Up to 5%; may drop to 2.5% at 50% completion 61 O.S. 123-124
Prompt payment Not confirmed; check the solicitation —
Cooperative purchasing National county association and nationwide programs; not for construction 19 O.S. 1501(A)(3)(p)
Preferences and certifications Optional local preference up to 5% on construction; Oklahoma materials preference 61 O.S. 103(B); 61 O.S. 6
Architects and engineers Not confirmed; check the solicitation —

Who buys

Each county is governed by a board of county commissioners, which opens bids at an open meeting and awards them. The county purchasing agent mails and publishes notices, and requisitioning officers recommend purchases (19 O.S. 1505, per OSU Extension).

Goods and services

  • Threshold: purchases over $25,000, including rentals, leases and lease-purchases, must be competitively bid. Splitting purchases to avoid bidding is a misdemeanor and grounds for forfeiture of office (19 O.S. 1505).
  • Below $25,000: no statewide quote rule was confirmed. Oklahoma County says quotes are often recommended below the threshold and applies the $25,000 limit per department (Oklahoma County 2025 presentation).
  • No bids received: the purchasing agent may solicit quotes (OSU Extension, Chapter Four).

Construction and public works

Public construction contracts over $100,000, and construction management trade contracts over $50,000, use competitive sealed bidding (61 O.S. 103(A)). Rules for smaller construction tiers were not confirmed; check the solicitation.

  • Bid security: 5% of the bid, by certified or cashier's check, surety bid bond or irrevocable letter of credit (61 O.S. 107).
  • Bonds: a 100% bond for performance and for payment of subcontractors, labor and materials, plus a 100% maintenance bond (or letter of credit) for one year after acceptance. The contract isn't executed until bonds and insurance are delivered (61 O.S. 113, per OSU Extension).
  • Road and bridge work: the county notifies ODOT at least 21 days before accepting bids (OSU Extension, Chapter Five).

Notice and award

Purchases: the purchasing agent mails notice to likely bidders and publishes it once in a newspaper of general circulation, at least 10 days before opening. The board compares bids with state contract prices at opening and awards within 30 days to a single vendor at the lowest and best bid. If it isn't the lowest bid, the reasons are recorded (19 O.S. 1505(B)).

Construction: notice runs in two consecutive weekly issues of a newspaper in the county where the work is done, the first at least 21 days before opening, plus electronic notice and notice to an in-state trade or construction magazine (61 O.S. 104; OSU Extension). The award goes to the lowest responsible bidder within 30 days of opening, which can be extended (61 O.S. 103(A), 113). Awarding to anyone else requires a public statement of reasons (61 O.S. 117).

A statewide RFP option for counties was not confirmed.

Prevailing wage

Oklahoma has no state prevailing wage law; it was invalidated by a 1995 court decision (U.S. Department of Labor). Federally funded work may still require Davis-Bacon wages.

Getting paid

On construction, the county may hold up to 5% of each partial payment as retainage, and may cut it to 2.5% at 50% completion. Payments require architect or engineer certification (61 O.S. 123-124, per OSU Extension). The retainage release deadline and a county prompt payment rule were not confirmed; check the contract.

Cooperative purchasing and state contracts

Counties may buy through nationwide programs sponsored by the national county association, local cooperative agreements and other competitively bid nationwide programs. These can't be used for Title 61 construction (19 O.S. 1501(A)(3)(p), per OSU Extension). Counties may also buy from state agencies and political subdivisions subject to the Central Purchasing Act after verification (OSU Extension, Chapter Six). See cooperative purchasing.

Preferences and required certifications

  • Local preference: on Title 61 construction, a local bidder within 5% that is second-lowest may match the low bid and win. OSU Extension describes it as applied under a county policy finding economic benefit (61 O.S. 103(B)); whether it is mandatory or optional is not confirmed.
  • Oklahoma materials: public buildings, including county institutions, have an Oklahoma materials preference (61 O.S. 6), and county hospitals have their own preference (19 O.S. 788) (Texas Comptroller summary).
  • E-Verify: 25 O.S. 1313 bars public employers from contracts for physical services unless the contractor uses a status verification system. Its application to counties was not confirmed.

Israel boycott, divestment and non-collusion requirements for counties were not confirmed; check the solicitation.

Architects and engineers

No county qualifications-based selection statute was confirmed. Check the solicitation.

Recent changes

  • Nov. 1, 2025: 2025 SB 403 took effect, amending 19 O.S. 1501 and 1505 on purchasing agent duties and removing a once-only alternative purchase limit of $25,000 or less (secondary: PolicyRisk). New dollar amounts, if any, were not confirmed.

Practical tips for Oklahoma

  • Ask the purchasing agent to add you to the mailing list; purchase notices are mailed to likely bidders.
  • Know the state contract price. Counties compare bids with state contract prices at opening.
  • Line up your bonding before bidding construction; you need 5% bid security and 100% performance, payment and maintenance bonds.
  • Check Oklahoma counties for each county's bid platform, contacts and agendas.

Questions

What is the bid threshold for Oklahoma counties?

Purchases over $25,000, including rentals, leases and lease-purchases, must be competitively bid. Splitting purchases to avoid bidding is a misdemeanor and grounds for removal from office (19 O.S. 1505, per OSU Extension).

How are Oklahoma county bids advertised?

For purchases, the purchasing agent mails notice to likely bidders and publishes it once in a newspaper of general circulation at least 10 days before opening (19 O.S. 1505). For construction, notice runs in two consecutive weekly issues of a county newspaper, the first at least 21 days before opening, plus electronic notice (61 O.S. 104).

Who wins an Oklahoma county bid?

For purchases, the board of county commissioners awards within 30 days to the lowest and best bid and records reasons if it isn't the lowest (19 O.S. 1505(B)). Construction goes to the lowest responsible bidder (61 O.S. 103(A)).

What bid security and bonds do Oklahoma counties require on construction?

A 5% bid guarantee by certified or cashier's check, bid bond or irrevocable letter of credit (61 O.S. 107), then 100% bonds for performance and payment and a 100% one-year maintenance bond (61 O.S. 113, per OSU Extension).

Can Oklahoma counties buy through cooperatives?

Yes, for non-construction purchases: national county association programs, local cooperative agreements and other competitively bid nationwide programs (19 O.S. 1501(A)(3)(p), per OSU Extension). They can't be used for Title 61 construction.

Does Oklahoma have a prevailing wage law?

No. Oklahoma's law was invalidated by a 1995 court decision (U.S. Department of Labor).

Sources

Last reviewed Oct 31, 2026. This is general information, not legal advice. Laws and thresholds change; check the current statute and the bid documents.